Business
Kurri gas plant could be running on diesel for months – ABC News
A gas-fired power plant proposed for the NSW Hunter Valley could be be waiting for up to six months for a gas connection, and critics say that’s indicative of the…

Plans for a taxpayer funded gas-fired power plant in the Hunter Valley have been labelled a “shambles”, after it was revealed it may have to run on diesel for its first six months.
Key points:
- If approved, a new gas-fired power plant could be complete in the Hunter Valley by late 2023
- An Environmental Impact Statement warns the plant’s gas pipeline may not be ready by then
- Green groups are worried that diesel could be used to run the plant for up to six months
The government-owned Snowy Hydro Corporation…
Continue Reading
-
General13 hours ago
Man arrested after alleged carjackings, dramatic pursuit in Melbourne CBD
-
Noosa News19 hours ago
Opera brilliance in Noosa | Noosa Today
-
Business15 hours ago
Buy these ASX dividend shares for 4% to 6% yields
-
General16 hours ago
Six NRL players named in England rugby league Ashes sqaud, Man of Steel winner not selected