OZ Minerals completes Carrapateena ramp up – Australian Mining

OZ Minerals has increased the production rate at the Carrapateena copper-gold mine in South Australia, achieving a planned ramp up ahead of schedule.

Published

on

post featured image

The Carrapateena mine in South Australia. Image: OZ Minerals
OZ Minerals has increased the production rate at the Carrapateena copper-gold mine in South Australia, achieving a planned ramp up ahead of schedule.
The company has achieved a rate of 4.25 million tonnes a year consistently during the month of November, despite a three-day COVID-19 lockdown being implemented across the state.
OZ Minerals completed the ramp up within 12 months, which was six months earlier than planned.