MULTIPLE SITE CONSTRUCTION Work on replacing Orealla Crescent Bridge at Sunrise…
????MULTIPLE SITE CONSTRUCTION????
Work on replacing Orealla Crescent Bridge at Sunrise Beach is progressing well.
Parallel to on-site works, several bridge components are being constructed at precast facilities in Brisbane and Beaudesert.
Vertical bridge wall panels are being fabricated off-site along with deck elements
A reminder, a detour is in place and the speed limit is 40kph.